Taribani Field Unit - Dino #2 Well Operations Gallery, May 2007 - April 2008
2007: Drilling operations for 2007 are focused on three wells in order to commence development of the Zone 9 horizon in the Taribani Field. The three wells scheduled for operations in 2007 are the Dino #2 (workover/recompletion), T-#45 and Taribani South #1.
May-June 2007: A dedicated drilling rig, the ARAR Dynamic #1, was mobilized from the United States, through the Bosporus of Turkey (shown below) and delivered to the Taribani Field.
June - July 2007: Preparation to commence workover/recompletion operations at the Dino #2 location, situated in the heart of Taribani Field Unit infrastructure.
July 2007: Preparation for commencement of operations at the Dino #2 location. The ARAR Dynamic #1 rig undergoing final technical inspection for operational readiness (left) while delivery of logging equipment from Baker Hughes takes place in anticipation of beginning work (right).
August 2007: Operations underway at the Dino #2 location in order to re-complete the well in Zone 9.
September 2007: Operations successfully completed at the Dino #2 location.
April 2008: Frac equipment on location at the Dino #2 location within the Taribani Field Unit.
April 2008: Frac operations underway at the Dino #2 location with the Taribani Field Unit.